the time of the 1980 NBC documentary ‘If Japan Can, Why Can’t We?’,
I was the System Manager in a video cassette manufacturing plant, and our
management team was asking this question every day.
Our Japanese competition was selling superior products at much
lower prices, and we couldn’t figure out how they did it.
We knew we needed to make dramatic changes or close up shop, but we
didn’t know what to change.
As far as we
could tell, we were doing everything right.
We relied on optimized forecasting methods to determine economic
lot sizes, and we used the latest MRP (Manufacturing Requirements
Planning) software to launch daily schedules into the plant.
We had a sophisticated computer system that analyzed QC results and
process parameters, to pinpoint the causes of defects.
We had some
quality problems, and it took a month to fill most
orders. In any given week, we
were able to pack out about 60% of the planned line items for the week.
But this was okay, because the other 40% of the week’s packout
went into finished goods inventory. Usually
we had plenty of on-hand inventory for shipping standard orders.
Special orders were another matter, however.
The division vice president would often call to expedite special
orders for important customers.
We moved
in-process video cassettes from one workstation to another on carts, and
we had a lot of carts. There
was never enough room to store all the carts at the next workstation, so
carts full of inventory would get misplaced.
Sometimes cassettes were stacked on top of carts, and occasionally
they would spill on the floor. Video
cassettes piled up in front of testing stations, so whenever a process
drifted out of control, it took a while to discover that we were producing
marginal product. We had plenty of rework stations, to be absolutely sure that
everything we shipped was good product.
All-in-all, we
had about a month’s worth of work-in-process inventory. At the time, we
blamed our inability to rapidly fill orders on bad forecasts from
marketing. Later we were surprised to learn that the real culprit was our
in-process inventory. Today
it is well known that the average shipping time of most supply chains is
about the same as the average level of inventory in the supply chain.
Lean Manufacturing
At the end of World War
II, Sakichi Toyoda, founder of Toyoda Spinning and Weaving company,
dreamed of providing cars for the general public, much like Henry Ford’s
dream thirty years earlier.
He chartered Taiichi Ohno to put in place an efficient production
system to produce high quality automobiles.
Over the next three decades, Ohno developed the Toyota Production
System, now known world-wide as Lean Manufacturing[1].
The foundation Ohno’s system was the absolute elimination of
waste.
Ohno studied US
manufacturing techniques, and learned a lot from Henry Ford’s pioneer
work in assembly line flow. However, the assembly line produced large lots of identical
cars. Ohno didn’t have the
customer base to imitate the US practice of manufacturing in
‘economic’ (ie. large) lot sizes.
He was captivated by US supermarkets, however, where a small
quantity of every product was placed on shelves, and as shoppers removed
products, the shelves were rapidly replenished.
He decided to place inventory ‘supermarkets’ throughout his
plant, and found that this technique dramatically lowered the ‘waste’
of in-process inventory. He
named these inventory supermarkets ‘kanban’.
Because Ohno
was converting a spinning and weaving company to an automobile
manufacturer, he already knew how to avoid making bad product.
Founder Toyoda Sakichi had invented an automatic shut-off mechanism
that stopped a weaving machine the minute a flaw such as a broken thread
was detected. Ohno moved this concept to car manufacturing, where he
insisted that each part be examined immediately after it was processed,
and the line stopped immediately if a defect was found.
To maximize
product flow, standard work sheets were created, but these were not
developed at a desk by engineers. They were developed on the shop floor by the workers who know
the process. Standard cycle
times and kanban shelf space for each item was determined and workflow was
leveled. Production workers
were like a relay team, handing off the baton (product) to the next
person. The handoff required 100% quality and tight timing.
If things got delayed, teammates were expected to help each other
set up a machine or recover from a malfunction.
Ohno’s
aggressive elimination of waste led him to the twin values of rapid
product flow and built-in quality. Over time, Ohno discovered that these two values led to the
highest quality, lowest cost, shortest lead time products possible.
Total Quality Management
About the same
time, Dr. W. Edwards Deming was teaching Quality Management in Japan.
In fact, the Total Quality Management (TQM) movement cannot be
separated from Lean Manufacturing. Demming’s
photo is in the lobby of Toyota’s
headquarters, bigger than the photo of founder Toyoda Sakichi. Demming
didn’t find an audience in the US after WW II, because managers at the
time thought that poor quality was caused by people who just didn’t want
to do a good job. They
didn’t think there was much managers could do to improve quality except
exhort employees to do a better job.
Demming’s
basic message was that quality is a management responsibility, and poor
quality was almost always the result of systems imposed on workers which
thwarted people’s desire to do high quality work.
He taught the Japanese managers how to empower production workers
to investigate problems and systematically improve processes.
He taught that teamwork and long term, trust-based relationships
with suppliers were far better than adversarial relationships.
He emphasized a culture of continuous improvement of both processes
and products.
In the
1980’s, Demming’s fourteen points (See
Appendix 1) were studied by virtually every manufacturing manager.
Among these fourteen points are the well known mantra’s:
Don’t
Inspect Quality In.
Constantly Improve the System.
Break Down Barriers Between Departments.
But a few of
Demming’s fourteen points might seem revolutionary even today, such as:
Drive
Out Fear.
Eliminate Quotas, Numerical Goals and Merit Ratings.
Don’t Award Business Based on Price; Minimize Total Cost.
Paradigm Shift
When we first
heard about Lean Manufacturing, we thought it was a hoax.
Get rid of safety stock, don’t run machines at full capacity,
have suppliers deliver small lots on a daily basis?
This was so counter-intuitive, so against the paradigm of the day,
that the Japanese manufacturing techniques were widely discounted. TQM concepts were more intuitive, but alone they were not
enough to lift us out of our dire situation.
Desperate for a change, we decided to give Lean Manufacturing a
try, and in the end, it saved our plant.
The critical
step in implementing Lean Manufacturing in our plant was a carefully
planned changeover from push scheduling to pull scheduling.
We decided that we could not do it part way, we had to switch
plant-wide, cold turkey, over a weekend.
We devised a simple simulation which we taught to every one in the
plant – managers, shift supervisors, and operators.
Using the simulation, teams of workers designed the layout and flow
in their areas, including the kanban cards and rapid changeover methods.
The entire plant held its collective breath as the pull system went
into effect, but the workers knew what to do – they had developed the
methods themselves. The first
week packout accuracy was 92%, and it got better from there. We were able to fill special orders in two weeks, so the vice
president could stop expediting orders.
In a short time we were down to one week of inventory and could
fill any order in the same amount of time.
We had lots of extra space, and quality had never been better.
The most
difficult part of implementing Lean Manufacturing was the paradigm shift
it required. Everyone
‘knew’ that large lot sizes were necessary to keep expensive machines
running at full capacity. They
also ‘knew’ that machine changeovers took a long time, and every
minute a machine was idle its burden rate went up. In addition, large warehouse inventories were necessary to
make sure that when a customer ordered a product it could be shipped
immediately. After all,
customers didn’t want to wait the month it took us to produce the
product.
One of the
reasons why Lean Manufacturing has been so difficult to implement is
because people must question established, known truths, and this is not
easy. Another reason is that
practices which create local optimization at the expense of the overall
system are difficult to recognize, let alone change.
Local optimization points provide attractive points of measurement,
and inevitably, what is measured is optimized.
Simple Rules
In a January
2001 article in Harvard Business Review titled ‘Strategy as Simple
Rules’, Kathleen Eisenhardt describes how smart companies thrive in a
complex business environment by establishing a set of simple rules which
define direction without confining it.[2]
She suggests that instead of following complex processes, using
simple rules to communicate strategy is the best way to empower people to
seize fleeting opportunities in rapidly changing markets.
The 1980’s
were a time of profound change in US manufacturing, and the change was
guided by a set of simple rules. Simple
rules gave guidance to every level of the organization, and got everyone
on the same sheet of music. They
empowered people at all levels of the organization, because the provided
guidance for making day-to-day decisions.
With simple rules, work teams were able to continuously improve the
processes and products without detailed guidance or complex processes.
The basic
practices of Lean Manufacturing and TQM in the 1980’s might be summed up
in these ten simple rules:
-
Eliminate
Waste
-
Minimize
Inventory
-
Maximize
Flow
-
Pull
From Demand
-
Empower
Workers
-
Meet
Customer Requirements
-
Do
it Right the First Time
-
Abolish
Local Optimization
-
Partner
With Suppliers
-
Create
a Culture of Continuous Improvement
These Lean
Manufacturing rules have been tested and proven over the last two decades.
They have been adapted to logistics, customer service, health care,
finance, and even construction. The
application of the rules may change slightly from one industry to the
next, but the underlying principles have stood the test of time in many
sectors of the economy.
Lean Programming
Recent work in
Agile Methodologies, Adaptive Software Development, and Extreme
Programming have in effect applied the simple rules of Lean Manufacturing
to software development. The
results, which we call Lean Programming, are as dramatic as the
improvements in manufacturing brought on by the Just-in-Time and Total
Quality Management movements of the 1980’s.
Lean Rule #1: Eliminate
Waste
The first rule
of Lean Programming is: Eliminate
waste. That is, eliminate anything which does not add value to the
final product. In Lean
Manufacturing, waste is identified through a value stream analysis, a
process which identifies all activities in the value stream and identifies
the specific value they add to the final product. The value analysis
process then attempts to find a different, more efficient way to add the
same value,
The documents,
diagrams, and models produced as part of a software development project
are often consumables, aids used to produce the system, but not
necessarily a part of the final product.
Once a working system is delivered, the user may care little about
the intermediate consumables. Lean principles suggest that every consumable is a candidate
for scrutiny. The burden is
on the artifact to prove not only that it adds value to the final product,
but also that it is the most efficient way of achieving that value.
Lean Rule #2: Minimize
Inventory (Minimize Intermediate Artifacts)
In our
manufacturing plant, we communicated this message:
Inventory is waste. Why?
Inventory consumes resources.
Inventory slows down response time.
Inventory hides quality problems.
Inventory gets lost. Inventory
degrades and becomes obsolete. The
‘benefits’ of inventory are oversold.
The ‘cost’ of inventory almost always outweighs such
‘benefits’.
The inventory
of software development is documentation that is not a part of the final
program. As inventory, this
documentation should be subject to value analysis.
Take requirements and design documents, for example. How much value
do the really add? How
important are they to the final product? If you compare requirements and design documents to
in-process inventory, then it is striking to note that the time it takes
to produce these documents probably determines the cycle time of the
project. Just as inventory
must be minimized to maximize manufacturing flow, so too requirements and
design documents must be kept to a minimum to maximize development flow.
There are many
wastes associated with this excess documentation:
The waste of time producing the documents, waste of time reviewing
the documents, and the work that goes into change requests and associated
evaluations, priority setting, and system changes.
But the biggest waste of all is the waste of building the wrong
system if the documentation does not correctly and completely capture the
user requirements.
The best
approach for minimizing intermediate artifacts is to raise the level of
abstraction of documentation. Instead of a 100 page detailed specification, write a 10 page
set of rules and guidelines, and document only the exceptions.
Instead of a few inches of specifics, produce a concise 25 page
matrix which summarizes the effort.
We know that
users are relatively poor at envisioning the details of a system from most
documents, and are even less likely to correctly perceive how it should
operate in their environment until they actually use it.
Even if users could predict exactly how the system should operate
at the present time, it is unlikely that the way the system is supposed to
work months before it is delivered will be exactly the way users need it
to work for the rest of its useful life.
All of this must be taken into account when we determine how much
value these documents actually add to the final product.
Lean Rule #3: Maximize
Flow (Drive Down Development Time)
During the
1980’s we learned how to make products in hours which used to take days
or weeks. We learned that
very rapid product flow resulted in very short cycle times, often one or
two orders of magnitude lower than before. During the 1990’s, e-commerce projects were often able to
accomplish in weeks what used to take months or years in the traditional
software development world. Yes,
in some sense they cheated. But
the bottom line is, huge amounts of useful software was deployed in the
last five years with extremely short cycle times by traditional standards.
In a recent
paper titled ‘Reducing Cycle Time,’[3]
Dennis Frailey proposes
reducing software development cycle time using the same techniques
employed to reduce manufacturing cycle time.
He suggests looking for and reducing accumulations of WIP (Work in
Process). Just as in
manufacturing, if WIP is reduced, and the cycle time will be reduced.
To reduce WIP, Frailey recommends using the ‘Small Batch’
principle and the ‘Smooth Flow Principle’, concepts straight from Lean
Manufacturing.
Iterative
development is basically the application of these principles to
programming. The basic
premise of iterative development is that small but complete portions of a
system are designed and delivered throughout the development cycle, with
each iteration adding an additional set of features. The cycle time from start to finish of any iteration varies
from a couple of weeks to a couple of months, and each iteration engages
the entire development process from gathering requirements to acceptance
testing.
Lean Rule #4: Pull from
Demand (Decide as Late as Possible)
In our video
cassette manufacturing plant, we used to think that it would be ideal if
our marketing department could forecast exact market requirements.
A lot of work went into sophisticated forecasting techniques to
more accurately predict the future. Then one day we realized that we were trying to do the wrong
thing. It would not
be ideal if we had a perfect forecast.
Instead, it would be ideal if we could reduce our reliance on
forecasts by reducing the system response time so dramatically that the
system could respond to change rather than predict it.
In a market
where volatile technology requires constant product upgrades, Dell
Computer has a huge advantage over it’s keenest competitors because it
doesn’t forecast demand, it responds to it by making-to-order in an
average of six days. While
Dell holds about six days of inventory, it’s competitors maintain six
weeks of inventory. Dell’s
ability to make decisions as late as possible gives Dell a significant
competitive advantage in a fast-moving market.
Software
development practices which keep requirements flexible as close to system
delivery as possible can provide a significant competitive advantage in a
changing market. In a
volatile business environment, users are not able forecast their future
needs accurately. Freezing
the design early in a software development project is just as speculative
as forecasting. Software
systems should be designed to respond to change, not predict it.
In software development, as in building computers, the ability to
make decisions as late as possible provides a competitive advantage.
Lean Rule #5: Empower Workers
(Decide as Low as Possible)
A basic
principle of Lean Manufacturing is to drive decisions down to the lowest
possible level, providing both the tools and the authority for people
“on the floor” to make decisions. When Toyota took over GM’s
manufacturing plant in Fremont, California in 1983, it inherited workers
with the worst productivity and absenteeism record in the industry. Those
same workers doubled their quality and productivity record in two years.
This was accomplished through formation of teams that were trained in work
measurement and improvement techniques and expected to develop and
continually improve their own work standards and practices.[4]
One of the
problems with heavyweight intermediate documentation is that it attempts
to make all of the decisions for developers, rather than giving them a set
of guidelines. In general,
raising the level of abstraction of intermediate artifacts will give
guidance as well as freedom to the developers as they make the detailed
design and programming decisions. It
is always better to tell developers what needs to be done, not how to do
it.
Developers need
to understand the goal of their work and how it fits into the overall
flow, what it means to meet customer requirements, and the architectural
structure and GUI standards of the system.
They also need to know what they must accomplish, by when, and how
to tell when it is complete. Finally,
their work needs to be made visible in short iterative cycles to provide
the feedback necessary for continual improvement.
Lean Rule #6: Meet
Customer Requirements (Now and in the Future)
In his 1979
book ‘Quality is Free’, Philip Crosby defines quality as
‘conformance to requirements’.
The Standish Group study of 1994[5]
noted that the most common cause of failed projects was missing,
incomplete, or incorrect requirements.
The software development world has responded to this risk by
amplifying the practice of gathering detailed user requirements and
getting user sign-off prior to proceeding with system design.
However, this approach to defining user requirements is deeply
flawed.
I
worked on one project in which the customer wanted a complex system
delivered in ten months. Time
was of the essence – 10 months or bust.
And yet, being a government agency, the contract required sign-off
on an external design document before internal design and coding could
begin. Several users were
involved, and they dragged their feet on signing the documents.
Why? They were
concerned that they might approve something which would prove to be a
mistake later on. Since there was no easy way to change things after the design
documents were signed, they took two months to approve the design.
An who can blame them? Their
jobs depended on them getting it right.
So half way into a very tight schedule, over two months of time and
a lot of paper was wasted producing and getting user sign-off on design
documents.
Instead of
encouraging user involvement, user sign-off tends to create an adversarial
relationship between the developers and the users.
Users are required to make decisions early in the development
process, and are not allowed to change their minds, even when they do not
have a full concept of how the system will work or how their business
situation may develop in the future.
Users are understandably reluctant to make these commitments, and
they will instinctively delay decisions to as late in the process as
possible. Note that this
instinct on the part of the users is in line with Lean Rule #4.
The most
effective way to accurately capture user requirements is found in the
iterative approach to system development.
By developing core features early and obtaining customer feedback
in a focus-group demonstration of each iteration, a far more correct
definition of customer requirements can be obtained.
In addition, if we accept that the requirements will necessarily
change over time, we must start with the essential requirement that the
system must be designed to easily adapt to changes over its lifecycle.
Lean Rule #7: Do it
Right The First Time (Incorporate Feedback)
Before Lean
Manufacturing arrived at our plant in the early 1980’s, we occasionally
had output of marginal quality. We would test to find the good product and
rework the bad product. After understanding the “Do it Right the First
Time” rule, we closed down rework stations and stopped trying to test
quality into the product. Instead, we assured that each component was good
at every handoff. This
involved having tests and controls at every point of manufacture to detect
a drift toward out-of-spec product and stop production before any bad
product was made.
“Do It Right
the First Time” did not mean “Freeze the Spec”.
On the contrary, product specs changed constantly, and lean
discipline meant being able to flawlessly adapt to changing market
conditions. This was accomplished through a product architecture which
facilitated manufacturing change, monitoring techniques which detected
errors before they happened, and tests which were designed before
manufacturing began.
In 1987 Barry
Boehm observed that it costs 100 times more to find and fix a problem
after software delivery than to find and fix it in early design phases.[6] This observation and the
“Do it Right the First Time” rule have been widely used to justify the
overhead of developing a detailed system design before code is written.
The problem
lies in the assumption that it is possible to generate a detailed set of
documents that correctly define customer requirements, and that those
requirements will not change. The fact is that requirements do change, and
frequently, over the life of most systems. “Do it Right” has also been
misinterpreted to mean “don’t allow changes.” In fact, once we
acknowledge that change is a fundamental customer requirement, it becomes
clear that what “Do it Right” requires that we provide for change.
If we want to
meet customer requirements, and we acknowledge that customers don’t
really know what they want at the beginning of development, then we need
to incorporate a method of obtaining customer feedback during development.
Instead, most software development practices include a “Change
Control Process” which makes it so difficult to respond to user feedback
that developers are discouraged from asking for it.
Far from insuring a quality result, these change-resistant
practices actually get in the way of “Doing it Right”.
Lean
Programming employs two key techniques that make change easy. Just as Lean
Manufacturing builds tests into process so as to detect when the process
is broken, Lean Programming builds tests into the development process in
order to ensure that when changes don’t inadvertently break the code. In
fact, the best approach is to write the tests first, and then write the
code. An excellent unit and regression testing capability is the best way
to encourage change late in the development process.
The second
technique for allowing change to happen late in development is
refactoring, or improving the design of existing software in a controlled
and rapid manner. When refactoring is an accepted practice, early designs
can focus on the issue at hand rather than speculate as to what additional
design elements will be needed. As the additional features are actually
added, refactoring provides a new, simplified design to handle the new
reality. When refactoring is a part of the process, we reduce speculation
as to what will be needed in the future by making it easy to accommodate
the future if and when it becomes the present.
Lean Rule #8: Abolish Local
Optimization
(Sub-Optimized Measurements are the Enemy)
In the 1980s,
the biggest enemy of Lean Manufacturing was often the accounting
department. We had big, expensive machines in our plant, and the idea that
they should not be run at full capacity was radical, to put it mildly. We
compiled daily reports of work-in-process inventory, and the accountants
didn’t want these reports abandoned just because there was virtually no
WIP to report.
A generation of
accountants had to retire before it was “OK” to run machines below
their full capacity. Designing machines for rapid changeover rather than
highest throughput remains a tough sell even today. After 20 years, Lean
Manufacturing is still counter-intuitive to those who lack a broad view of
the enterprise.
In this
context, let’s examine the role of managing scope in a software
development project. Project managers have been trained to focus on
managing scope, just as we in manufacturing were trained to focus on
maximizing machine productivity. However, Lean Programming is
fundamentally driven by time and feedback. In the same way that localized
productivity optimization creates a sub-optimized overall process, so too,
does focus on managing scope create a sub-optimized overall project
management process.
Think about it
– holding the scope to exactly what was envisioned at the beginning of a
project has little value for the user whose world is changing.
In fact, it adds anxiety and paralyzes decision-making.
It doesn’t add much to the ultimate system, which will be
outdated by the time it is delivered. Managing to a scope that is no
longer valid wastes a lot of time and takes up a lot of space on issue
lists, trade-off negotiations and ultimate fixes to the system to get
things right in the end. However, as long as keeping a project within its
original scope is a key project management goal, this measurement will
continue to be optimized—at the expense of the overall value delivered
by the project.
Scope will take
care of itself if the domain is well understood and there is a
well-crafted, high-level agreement on what the system will do in the
domain. Scope will take care of itself if the project is driven in time
buckets that are not allowed to slip. Scope will take care of itself if
both parties focus on rapid development and solving the user’s problem,
and adopt waste-free methods of achieving these goals.
Lean Rule #9: Partner With
Suppliers (Use Evolutionary Procurement)
Lean
Manufacturing did not remain in the manufacturing plant. Once the idea of
partnering with suppliers was combined with an understanding of the value
of rapid product flow, Supply Chain Management was born. People began to
realize that it took tons of paperwork to move material between companies,
and this did not add value to the product. Moreover, the paperwork cost
more than one might expect, not to mention the delay in product flow that
it caused. Even today, predictions of billions of dollars of savings
resulting from business-to-business Web portals are based on cutting the
cost of transactions required to move goods between companies.
Supply Chain
Management caused companies to take a close look at their
business-to-business contracts. All too often, these contracts were
focused on keeping the companies from cheating each other. In addition, it
was common to pit one vendor against another to assure supply and obtain
the lowest cost. Again, Lean Manufacturing changed this paradigm. Deming
taught that trusting relationships with single suppliers create an
environment that allows optimizing the overall value to both companies.
Throughout the
1980s, companies achieved the highest quality and lowest costs in their
supply chains by reducing the number of suppliers and working with the
remaining suppliers as partners. The quality and creativity which resulted
from collaborating supply chains was demonstrated to far outweigh the
apparent (and sub-optimal) benefits that came from competitive bids and
rapid turnover of suppliers. Partnering companies helped each other
improve product designs and product flows. They linked systems to allow
just-in-time movement of goods across several suppliers with little or no
paperwork. The long-term advantages of a collaborative supply chain
relationships are well documented.
Wise companies
realize that traditional software development contract practices generate
hidden wastes. As manufacturers discovered in the 1980s, trusted
relationships with a limited set of suppliers can yield dramatic
advantages. Without the adversarial relationship created by a constant
focus on controlling scope and cost, software development vendors can
focus on providing the best possible software for customers, fixing
requirements as late as possible in the development process and providing
the most value for the available money.
Lean Rule #10: Create a
Culture of Continuous Improvement
When software
development seems to be out of control, one response has been to increase
the level of “software maturity” of the organization. This might seem
to be in line with good manufacturing practice, where ISO 9000
certification and Malcom Baldridge awards are sometimes equated with
excellence. However, these process documentation programs indicate
excellence only when the documented process is excellent in the context of
it’s use.
In many current
software development projects, excellence means the ability to adapt to
fast moving, rapidly changing environments.
Process-intensive approaches such as the higher levels of Software
Engineering Institute's (SEI) Capability Maturity Model (CMM) may lack the
flexibility to respond rapidly to change.
In a recent e-mail advisor from Cutter Consortium, Jim Highsmith
highlights the tension between such heavyweight methodologies and
lightweight methodologies such as Lean Programming.[7]
The question
becomes, do process documentation certification programs stifle, rather
than foster, a culture of continuous improvement?
Deming would probably turn over in his grave at the thought of
tomes of written processes substituting for his simple Plan-Do-Check-Act
approach:
Plan:
Choose a problem. Analyze it to find a probable cause.
Do: Run an experiment to
investigate the probable cause.
Check: Analyze
the data from the experiment to validate the cause.
Act:
Refine and standardize based on the results.
Iterative
development allows the use of the Plan-Do-Check-Act approach within a
project. During the first iteration, the hand-off from design to
programming or programming to testing may be a bit rough. It’s okay if
the first iteration provides a learning experience for the project team,
because there are more iterations to come, so the team can improve its
process. In a sense, an iterative project environment becomes an
operational environment, because processes are repeated and Deming’s
techniques of process improvement can be applied from one iteration to the
next.
Product
improvement is also possible with iterations, particularly if refactoring
is used. In fact, refactoring provides a tremendous vehicle to apply the
principle of continuous improvement to the programming environment.
However, we
need improvements that span more than a single project. We must improve
future project performance by learning from existing ones. Here again,
Lean Manufacturing can point the way. During the 1980s, a set of practices
summarized in the ten rules of Lean Manufacturing were adopted widely
across most manufacturing plants in the West. These practices then spread
to service organizations, to logistics organizations, to supply chains,
and beyond. They have withstood the test of time across multiple domains.
Following the
simple rules of Lean Manufacturing has brought dramatic improvements to
every industry in which they have been applied. These same rules can and
should be applied to software development projects. The resulting Lean
Programming practices will lead to the highest quality, lowest cost,
shortest lead time software development possible.
Appendix 1: Summary of W.
Edwards Demming’s 14 points
-
Create
consistency of purpose.
-
Adopt
a win-win philosophy.
-
Don’t
depend on mass inspection; build quality in.
-
Don’t
award business based on price; minimize total cost; build long-term
relationships of loyalty and trust with a single suppliers.
-
Constantly
improve the system of production, service, planning, etc.
-
Train
for skills.
-
Provide
leadership: help people
do a better job.
-
Drive
out fear and build trust so everyone can do a better job.
-
Break
down barriers between departments; abolish competition and build a
win-win system of cooperation.
-
Eliminate
slogans, exhortations and zero defect targets; the cause of the bulk
of problems lie in the system, and are beyond the power of workers to
correct.
-
Eliminate
quotas, numerical goals and Management by Objectives; substitute
leadership.
-
Remove
barriers that rob people of joy in their work; abolish the annual
rating or merit system.
-
Educate
and improve individuals.
-
Involve
the entire organization.
There are many
summaries of Demming’s 14 points, which he modified throughout the
years, in the spirit of continuous improvement.
The above summary is based on his last version of the 14 points.[8].

[1]
The Machine That Changed the World : The Story of Lean
Production, by Womack, James P., Daniel T. Jones, and Daniel
Roos, New York: Rawson and Associates; 1990, ISBN: 0892563508
[2]
Strategy as Simple Rules, by Eisenhardt, Kathleen M and
Donald N. Sull, Harvard Business Review, Volume 79, Number 1,
January 2001, pp 107- 116
[3]
Reducing Cycle Time, by Frailey, Dennis, Software
Development Magazine, August, 2000
[4]
Time-and-Motion Regained,
by Paul Adler, Harvard Business
Review, January-February 1993 pp 97-108
[5]Charting
the Seas of Information Technology – Chaos, by The Standish
Group International, 1994
[6]
Industrial Software Metrics
Top 10 List, by Boehm, Barry, IEEE
Software, Volume 4 Number 5, September, 1987, pp 84-85
[7]
E-Projects in India,
by Jim Highsmith, e-Project Advisor, Cutter Consortium's
e-Project Management Advisory Service, March 1, 2001.
[8]
Gone But Never Forgotten, by Brad Stratton, editor, Quality
Progress Magazine, March 1994
Annotated Bibliography
(Chronological)
Quality Control Handbook, Joseph M. Juran,
originally published in 1951, now in its forth edition
Considered
the standard reference in the field of quality.
Like Demming, Juran consulted mainly in Japan during the
1950’s and 60’s.
Managerial Breakthrough, Joseph M. Juran,
originally published in 1964
Widely
ignored when it was first published, this book is now considered a
landmark treatise on continuous improvement.
Quality is Free, by Philip Crosby, New York:
McGraw-Hill, Inc. 1979
This
is the book we used to launch the TQM program in our plant.
Demming never liked the zero defects approach advocated in this
book, and it contains little about statistical quality control.
However, many corporate executives got the quality message from
Phil Corsby.
Study of ‘Toyota’ Production System from Industrial
Engineering Viewpoint, by Shigeo Shingo, Osaka, Japan, Shinsei
Printing Co. Ltd. 1981
The
title of this book is an indication of the quality of the translation,
but that was not a barrier to our plant.
We studied the book cover-to-cover and got our introduction to
Lean Manufacturing from this book.
Toyota
Production System, Practical Approach to Production Management,
by Yasuhiro Monden, Norcross, Georgia, Industrial Engineering and
Management Press. 1983
This
is the classic book on Lean Manufacturing.
Zero
Inventories, by Robert W. Hall, Homewood, IL, Dow Jones-Irwin
1983.
Robert
Hall, a professor at Indiana University, understood the concept of
Just-in-Time earlier than most academics.
This book is still considered the definitive work on JIT.
A Revolution in Manufacturing, the SMED System,
by Shigeo Shingo, Cambridge, MA, Productivity, Inc. Originally published as Shinguru Dandori in 1983,
English translation 1985.
The
title of this book is an indication of the quality of the translation,
but that was not a barrier to our plant.
We studied the book cover-to-cover and got our introduction to
Lean Manufacturing from this book.
The Goal, by Eliyahu M. Goldratt, First Edition
Published in 1984, Second Revised Edition Published in Great
Barrington, MA, 1992
This
book is a business novel. It
is the easiest book to read for an introduction to Lean Manufacturing
and is definitely a classic. You
will find this book on the reading list of most Operations Management
courses. Goldratt went on
to develop the ‘Theory of Constraints’ and write several related
business novels.
Out of the Crisis, by W. Edwards Demming; 1986
This
is the book in which Demming outlined his famous 14 points.
The Demming Management Method, by Mary Walton and
W. Edwards Demming; 1988
Probably
the best book there is on Demming and his management approach.
Toyota Production System – Beyond Large Scale
Production, Taiichi Ohno, published in Japanese in 1978 and in
English in 1988 by Productivity, Inc.
This
is an explanation of JIT by the inventor. The English version arrived
after JIT had become widespread in the US.
The Machine That Changed the World : The Story of Lean
Production, by Womack, James P., Daniel T. Jones, and Daniel
Roos, New York: Rawson and Associates; 1990
This
landmark book about the Toyota Production System was the first to
associate the term ‘Lean’ with manufacturing.
Lean Thinking, by Womack, James P., and Daniel T.
Jones, Simon & Schuster; 1996
A
follow-up on the story of Lean Production, this book extends the
concept of Lean throughout the enterprise.
It shows how the "lean principles" of value (as
defined by the customer), value stream, flow, pull, and perfection can
be applied to all areas of the enterprise.
(Software development is implicitly included.)